The U.S. Space Force seeks a contractor to perform the complete physical relocation of fifteen large pieces of equipment between multiple buildings at Patrick Space Force Base, Florida. The contractor must supply all labor, material‑handling equipment, transportation, tools, supervision, and safety compliance, coordinating with an electrical contractor for lockout/tagout procedures. The effort must be completed within a 30‑day contract period, with the actual move executed in a consecutive 7‑day window. Government‑furnished equipment will be moved; the contractor is responsible for inventory, handling, route planning, protection of assets, and final placement sign‑off. Key deliverables include a relocation schedule, base‑access request list, and placement sign‑off documentation.
• Relocate 15 specified pieces of heavy equipment (e.g., heat‑treat oven, lathe, 3‑D printer) from Buildings 605, 607, 631/651, and 699 to Building 757.
• Provide forklifts, dollies, rigging, and other handling gear; ensure OSHA and Air Force safety compliance.
• Coordinate with Government POCs and the electrical contractor for LOTO and timing.
• Complete all work within a 7‑day continuous window, total contract duration 30 days.
• Submit relocation schedule (10 days post‑award), base‑access list (7 days pre‑start), and final placement sign‑off.