The San Jacinto Community College District (SJCCD) is issuing a Competitive Sealed Proposal (CSP) for electrical upgrades to three campus buildings (C30, C31, C32) at its Central Campus in Pasadena, Texas. The scope includes demolition of existing MV cabling, installation of new medium‑voltage (12.47 kV) distribution systems, grounding, conduit and duct bank work, earthwork, and site restoration. Contractors must handle utility locating, ground‑penetrating radar, concrete and compaction testing, and coordinate shutdowns—preferably during spring break. The project budget is roughly $280,000, with work slated to begin 30 Oct 2026 and finish by July 2027. Proposals must be submitted electronically via the IonWave e‑bidding system by 2 PM CT on 14 Oct 2026. A non‑mandatory pre‑proposal meeting is scheduled for 1 Oct 2026 at the campus. Key deliverables include compliance with NETA testing standards, ASTM compaction criteria, and Texas prevailing‑wage requirements.
• Electrical design, installation, and testing for three campus buildings
• Medium‑voltage conduit, duct banks, and cable reuse verification
• Required earthwork, compaction, and site restoration to pre‑construction condition
• Coordination of outages, utility locating, and testing (NETA, ASTM)
• All permitting, bonding, and prevailing‑wage compliance
• Project budget ~ $280 K; start 30 Oct 2026, complete July 2027.