The City of Grand Junction issued a design‑build solicitation (RFP‑5601‑25‑DD) to construct a next‑generation material recovery facility (MRF). Six firms submitted complete proposals, and the award was made to Bulk Handling Systems. The contract calls for full design, engineering, procurement, and construction of a modern MRF that meets state‑wide funding (SWIFR) requirements and includes advanced sorting equipment. The award decision was expected by May 20 2025, with the bid opening having occurred on April 21 2025.
• Scope: Design‑build of a material recovery facility, including equipment procurement, civil works, and compliance with SWIFR funding conditions.
• Awarded Vendor: Bulk Handling Systems (Eugene, OR) with a total equipment cost of roughly $10.7 M and additional cost items bringing the estimated contract value to about $14 M.
• Procurement Process: Open competition with bids opened on 4/21/2025 and the final award anticipated on 5/20/2025.