The Municipality of Skagway contracted a single vendor to upgrade the water distribution system serving the Pullen Creek RV Park. The work involves installing new 2‑inch HDPE water mains, 44 new service connections, valve boxes, trenching, back‑fill, erosion control, and associated site work, with a required completion date of mid‑October 2020. The contract was awarded to Hamilton Construction, LLC for a lump‑sum price of $167,525, following an open competitive bidding process that closed on August 24 2020. The procurement required no bid fee, no bid security, and a 60‑day bid validity period. Key points include:
• Scope: HDPE mains, service lines, valve installation, trenching, back‑fill, concrete work, and site restoration.
• Schedule: Bids due Aug 24 2020; award announced Sep 8 2020; work to be completed by Oct 15 2020.
• Financials: Fixed‑price contract at $167,525; performance and payment bonds not required (contract value below $150 k).