Description
This bid tabulation documents the public‑bid process for the City of Fort Smith’s Phase 2 basin capacity upgrades, encompassing extensive civil‑engineering and utility work. The project involves more than 120 line items, including concrete pavement, water and sewer pipe installation, manhole construction, erosion control, traffic control, and site‑development activities. Four contractors submitted bids, and the total of the corrected bids totals approximately $13.4 million, but no award has yet been made.
• Scope: Water‑sewer utility upgrades, road and pavement construction, structural and site works, and related ancillary services.
• Scale: Over 5,000 square yards of pavement, thousands of linear feet of pipe (including a 30″ sewer pipe worth $4 million), numerous manholes, and extensive earthwork.
• Procurement: Open public bidding with a bid opening on 21 Oct 2025; the bids were tabulated and certified the following day.
• Financial: Summed corrected bids equal $13,365,065; a $250,000 performance & payment bond is required.
• Status: Post‑bid tabulation only—no contract award, start date, or term has been announced.