This contract calls for a professional design‑services firm to develop complete roof‑replacement plans for Manchester Regional Academy, a public K‑12 school in Manchester, CT. The scope includes existing‑condition surveys, structural and drift‑loading analysis, schematic and construction‑document sets, preparation of the Connecticut DAS construction‑grant application (SCG‑049), cost estimating, bidding assistance, and construction‑administration services. The consultant must also secure a waiver of the state minimum roof‑pitch requirement and ensure compliance with all state, local, and federal building‑code and grant‑eligibility criteria.
• Design deliverables: schematic drawings, detailed construction documents, cost estimates, schedule, and grant‑application package.
• Regulatory work: DAS/OSCG grant preparation, energy‑code compliance, and pitch‑waiver analysis.
• Project phases: pre‑proposal conference (May 10 2017), proposal submission (May 22 2017), award recommendation (June 5 2017), grant filing (June 26 2017), design completion (early‑2018), construction start (June 25 2018) and completion (August 24 2018).