This is the Baruch College South Campus Boiler Upgrade / Boiler Replacement project for CUNY Baruch College, administered through DASNY. The work is centered on replacing/upgrading the South Campus central boiler plant serving campus buildings including Newman Hall at 137 East 22nd Street, the Field/Lawrence and Eris Field Building at 17 Lexington Avenue, and the Administration Building on East 22nd Street in New York City.
The project generally includes replacing the existing boiler plant with three new gas-fired fire-tube steam boilers, plus related burners, boiler-feed equipment, condensate/vacuum pumps, water treatment, steam and condensate piping, flues/breeching/stacks, controls/BAS integration, gas piping, electrical power, fire alarm/fire protection interfaces, and commissioning.
Supporting work includes selective demolition, asbestos abatement, lead/hazardous-material handling, concrete pads, structural steel/concrete work, roofing/flashing repairs, doors/frames, finishes, lighting, plumbing, sprinkler, and electrical distribution modifications.
Service-Disabled Veteran-Owned Business (SDVOB)
SDVOB Goal: 6.00%
Minority / Women Business Enterprise contracting goals (MWBE)
MBE Goal: 18.00%