This sole‑source professional‑services contract awards CDM Smith a $122,274 fixed‑price agreement to provide continued engineering services for the Tucumcari Reuse Project. The work covers construction‑phase engineering, project management, coordination with the city and New Mexico Environment Department, review of operation & maintenance manuals, response to RFIs, change‑order administration, site inspections, and final project close‑out documentation. Because CDM Smith is the Engineer of Record and the project is ~85 % complete, the city requires continuity of expertise to avoid schedule delays, cost overruns, and compliance risks with CWSRF funding. The contract runs from late August 2026 through the end of December 2026 (approximately 2.5–4 months).
• Scope: construction‑phase engineering, O&M manual review, RFIs, change orders, progress monitoring, final inspections.
• Value: $122,274 fixed‑price.
• Duration: ~4 months (Aug 21 2026 – Dec 31 2026).
• Sole‑source justification: unique project‑specific knowledge held only by CDM Smith.