This contract concerns the replacement and installation of Furnace #3 and its associated condenser at Fire Station #5, a municipal fire facility in Waukesha, Wisconsin. The solicitation was re‑issued (REBID) and is open for competitive bids, with a deadline of April 10, 2026. Bids submitted include two identified firms—August Winter & Sons, Inc. and a vendor listed as “UofM”—with quoted amounts ranging from roughly $42 k to $86 k. The city will award the contract to the lowest responsive and responsible bidder, and the work will involve HVAC system upgrades for a fire station, a typical small‑scale public‑sector construction project.
• Scope: furnace and condenser replacement for a fire station HVAC system.
• Procurement: rebid, full and open competition, lump‑sum pricing.
• Estimated contract value: under $100 k (highest bid $86,200).
• No awardee or contract dates are provided yet.