The City of Edmond is soliciting sealed bids for the design‑build construction of the NE Complex Phase 1, which involves relocating the Danforth Elevated Storage Tower (TWR‑3) and associated water‑utility infrastructure. The contractor must supply all materials, equipment, labor, and services required to demolish existing structures, perform site grading, install a new 0.5 MG DI water storage tank, lay new water and sanitary sewer pipelines, install SCADA and instrumentation, construct associated civil works (fencing, gates, storm‑drain structures), and complete all required testing, commissioning, and close‑out documentation. The work must be performed in accordance with the City’s plans and specifications, with a contract period of 580 calendar days, and includes performance, maintenance, and statutory bonds equal to 100 % of the contract price. Early‑completion incentives of up to $90,000 are offered, and liquidated damages of $1,000 per day apply for overruns.
• Relocation and installation of a 0.5 MG DI water storage tank (Danforth Tower)
• Demolition, site grading, and preparation of the NE Complex area
• Installation of new water mains (12” and 6” DI lines) and sanitary sewer lines (PVC)
• Construction of valve vaults, manholes, fire hydrants, and storm‑drain structures
• Provision of SCADA, instrumentation, and electrical systems for tank operation
• Required permits, inspections, testing (hydrostatic, disinfection) and commissioning
• Mandatory pre‑bid meeting (Nov 3, 2026) and bid bond of 5 % of the bid amount
• Contract duration 580 days with $1,000/day liquidated damages and $1,000/day early‑completion incentive (max $90,000)