The City of Garland is soliciting competitive sealed proposals for the design‑build construction of the Duck Creek Waste‑Water‑Treatment‑Plant (WWTP) Administration Operations Facility located at 750 Duck Creek Way, Sunnyvale, TX. The scope includes demolition of existing structures, site grading, utility installation, concrete work, structural steel, architectural finishes, laboratory casework, mechanical, electrical, plumbing, fire protection, and technology systems (AV, security, networking). The contractor is responsible for furnishing, installing, testing, and commissioning all equipment and finishes indicated on the plans, coordinating with the City’s engineering department, and complying with a wide range of codes (IBC, NEC, NFPA, ADA, etc.). The project is non‑residential, Class B occupancy, approximately 8,910 SF of building area on a 92,000 SF site, and must be completed in accordance with the City’s standard specifications for public works.
• Competitive sealed bid, electronic submission via Ion Wave eBid
• Pre‑bid meeting (Sept 23) and site visit (Sept 24) – both optional
• Questions due by Oct 9; bid close Oct 22
• No mandatory minority‑business participation goals
• Contractor must provide all construction sequencing, traffic control, erosion control, and utility protection measures
• Required coordination with laboratory testing firm (owner‑provided) and City engineering staff
• Full compliance with safety, environmental, and accessibility standards