The City of Lake City is seeking a qualified contractor to demolish, remove, and replace the roofing systems (roof panels, substructure, purlins, flashings, gutters, etc.) on two airport hangars (Hangar 1 and Hangar 2) at the Lake City Gateway Airport. The project is funded partially by the Department of Commerce Rural Infrastructure Fund and must comply with all federal, state, and local regulations, including OSHA, FAA, and 2 CFR Part 200. The contractor will be responsible for all permitting, material procurement, installation, waste disposal, site safety, and warranty compliance. Bids are submitted electronically via OpenGov, with a firm price required for 90 days and a performance period of 240 calendar days after equipment delivery. The award is expected on 21 Dec 2026, and the contract includes liquidated damages of $1,500 per day for late completion.
• Scope: Full demolition of existing roof, installation of new metal roof panels, purlins, accessories, and related waterproofing.
• Location: Lake City Gateway Airport, 3524 E HWY 90, Lake City, FL.
• Schedule: Pre‑bid meeting/site visit – Oct 29 2026 (optional); Questions due – Nov 5 2026; Bid submission – Nov 19 2026, 2 pm; Award – Dec 21 2026; Work completion – 240 days after start.
• Requirements: Contractor must hold all necessary licenses, provide insurance (CGL $1 M, Workers’ Comp, Vehicle/Umbrella $200‑300 k), submit bonds (5 % of contract), and comply with E‑Verify and DBE/MBE/WBE participation.
• Evaluation: Best value, with a 5 % preference for Columbia‑County residents.