The City of Rapid City is procuring filter media, underdrains, and troughs for the media filters at the Mountain View Water Treatment Plant. The existing equipment is past its useful life and requires replacement. The procurement is being done in advance of the installation contract due to anticipated long lead times. The bid results table lists several bidders, including AWI, Leopold, and Aerzen. The engineer's estimate for the project is $1,960,000.00.
• The project involves the replacement of filter media, underdrains, and troughs at the Mountain View Water Treatment Plant.
• The procurement is being done in advance of the installation contract due to anticipated long lead times.
• The bid results table lists several bidders, including AWI, Leopold, and Aerzen.
• The engineer's estimate for the project is $1,960,000.00.
• The advertising authority for the project is $2,600,000.00.