The Federal Bureau of Prisons is soliciting a firm‑fixed‑price construction contract to replace the existing 750 kW generator and associated equipment at Federal Correctional Institution‑Bastrop, Texas, and install a new 2000 kW diesel generator with switchgear. The work includes complete material procurement, labor, equipment, and compliance with BOP security, safety, and labor regulations. The contract is a small‑business set‑aside, requires SAM registration, and includes extensive security clearances for all personnel.
• Replace existing 750 kW generator, load bank, and 3‑way main switchgear.
• Install one new 2000 kW diesel generator and switchgear system.
• Provide all labor, materials, equipment, and required submittals; adhere to a 420‑day performance period.
• Must submit a 20 % bid bond (capped at $3 M) and meet extensive insurance, bonding, and security‑clearance requirements.
You found this one. Bid Banana has 1.6M+ bids and awards.
You found this bid by looking. Bid Banana searches open government bids across all 50 states, updated daily, so you stop hunting: save a search once and we email you your new matches, daily or weekly.